Central Otago District Council has approved a $3.023 million programme to tackle a major build-up of sludge at the Cromwell wastewater treatment plant, with existing dried material to be transported to a landfill in Winton.
A survey earlier this year identified about 20,000 cubic metres of sludge accumulated in Cromwell’s treatment ponds. According to the council, the material is now breaking the surface of Pond One, reducing available pond capacity and affecting treatment performance.
The council says leaving the build-up unresolved could also increase the risk of the plant reaching stricter nitrogen limits under its resource consent, potentially bringing forward the need for more expensive treatment upgrades.